Workshop roof rebuild May/June/July/August/September & October 2015

3 October, 2015

Final post re my workshop roof. Job completed all the walls have been pebble dashed and new rooller shutter door fitted.

To bring you up to date roof construction complete just waiting for 4 days of guaranteed dry weather to dry out before applying final covering. Photography stopped for a while as I am in the process of building a new roof on my garage/workshop here at home. Work proceeding well old roof gone and first half of new roof installed. Weather has been aproblem mainly wind as handling tarpaulin becomes hard work.Third picture shows two of the old roof timbers why the old roof needed replacing urgently. 

10/08/2015 Roof nearly finished after disaster with tarpaulins leaking and first set of top boards ruined. Now replaced and GPDM (ethylene propylene diene terpolymer) covering (but not fixed) at least we are waterproof.

15/08/2015 Roof finished GPDM stuck down and all trims added and guttering installed. Internal work (pointing & painting) left to do. Await pebble dasher to re do whole building then replace lean to roof at side of workshop.

October 2015 All pebble dashing completed and roller shutter door fitted.

 
Workshop roof rebuild May/June/July/August/September & October 2015
 
Workshop roof rebuild May/June/July/August/September & October 2015
 
Workshop roof rebuild May/June/July/August/September & October 2015
 
Workshop roof rebuild May/June/July/August/September & October 2015
 
 
Sign up for email promotions.
Your information is safe with us and won't be shared.
Thank you for signing up!
 

By continuing to browse or by clicking Accept Cookies, you agree to the storing of cookies on your device necessary to provide you with the services available through our website.

    Accept   Privacy & Cookie Policy
Loading More Photos
Scroll To Top
Close Window
Loading
Close